Production facilities of "Ekvator plant" JSC
Project
Owner "Ekvator" Plant" JSC
Intended for industrial purpose
Budget 1 500 000 EUR



Property Description
Actual use Cooling machines, air and heat-exchangers equipment and metal furniture production plant
Floor area 50 000 m2
Land area 750 m2
Surronding complex of apartment buildings, railway station, production facilities
Distanse to accommodation 250 m
Covering asphalt
Engineering facilities
Electricity Power class: II Voltage: 0,4 kV Power: 270 kW
Gas supply Efficiency: 250 m3/h Pressure: 3 atm
Water supply Efficiency: 10 m3/h
Sewage system Line diameter: 100 mm
Heat supply Line diameter: 160 mm
Telecommunication in-line



Project description
Goal of the project
Project implementation period Creation of a modern station for heat exchangers production - 6 months Creation of a robotic extrusion complex of rolled metal for the aluminum profiles production - 1,5 years



Transport infrastructure
To access roads access road adjacent
To international highways 1 km
To railways 0,5 km